Now that the concrete work is complete, roadway work will begin Thursday, August 25th. On this date, the roadway will be milled down approximately 5” to prepare for a new asphalt roadway. Residents will be temporarily displaced from their driveway for a few hours. If you need to get out of your driveway on this day, please remove your car and park on a side street on Wednesday night. No Parking will be allowed on Shabbona or South Orchard at this time.
We realize that this is an inconvenience and appreciate your patience. If you require special accommodations during this time, please call our office so that we may assist to the best of our abilities.
As a reminder, this project will take place during working hours, Monday-Saturday, 7am-6pm. Common construction inconveniences such as traffic congestion, dust, noise, and heavy equipment should be expected. Residents should be sure to keep a safe distance from construction equipment and be sure not to walk near construction activity.
We thank you in advance for your patience and cooperation as we complete this work. If you have any questions, please call (708) 503-7702.