2022 Street and Water Main Replacements

Replacement of water main and street resurfacing within the Village of Park Forest is partially financed by the Drinking Water State Revolving Fund (SRF). The SRF program is administered by the Illinois Environmental Protection Agency and receives a portion of its money to fund these types of projects from the U.S. Environmental Protection Agency. This project includes the replacement of water main and resurfacing of approximately 2.7 miles of streets as follows: Antietam, Arrowhead, Apache, Washington (Wilshire to Westgate), Washington Court, Windsor, Lester (Sauk to Indianwood), Apple, Nassau, Monee (Blackhawk to Orchard), and Monee Court. Once complete, it will improve water quality for area residents by reducing water main breaks and improving flow and pressure. SRF programs operate in each state to provide communities the resources necessary to build, maintain, and improve the infrastructure that protects one of our most valuable resources: water 

View All Posts

Jun 15

06/15/22 Update

Posted on June 15, 2022 at 2:23 PM by Nick Christie

The Water Main installation is almost complete on Antietam. Work continues on Winsdor and the pipe should be 90% installed by Friday. On Tuesday, 6/21, work will move to Washington Street. On Friday 6/17 and Tuesday 6/21,there will be water outages near Washington Street. Affected residents will be notified. No parking will be allowed on the streets currently under construction.  

Comments

You must log in before leaving your comment